Hi,
In XPE for series-7, we first filled up the "Device", "Environment", "Implementation" parts of the
summary sheet & then performed Quick Estimate. We have observed that after Quick estimate,
several fields, such as, junction temperature etc changes automatically. If we manually
revert back these field values to the original ones, Power requirement changes.

In what order should the values be entered? first into "Device", "Environment",
"Implementation" & then perform Quick Estimate or vice versa?
Which Power value is the actual one?